During the second phase contract, E-Schakt will remove 5.5 m of concrete on the vertical element of the upstream side of the dam to a depth of 200 mm; including at least 1 m underwater.
For this operation, the Aqua Frame robot will be positioned on the vertical upstream damwall and be secured to the wall by divers. Then, in close collaboration with the Skanska divers, the E-Schakt operator can continue the under water hydrodemolition operation remotely from above the surface.
The Aqua Frame includes 8 meter side rails with a 4 meter traverse rail to support the oscillating lance in the traversing power head with its nozzle to continue operating at 1000 bar at a rate of 260 l/min – 330 l/min depending on the removal depth.
Spillway gates
The Järpströmmen installation features three steel spillway gates, one with a gate well and two without a well, featuring concrete slab spillways.
The three gates provide a total length of almost 60 m and a maximum height of 16 m.
Throughout each of the three phases of refurbishment, a single gate will be removed in turn for blasting and retreatment. Hydrodemolition techniques on all concrete structures to the gates will follow removal of the gate.
This aspect would normally provide problems for contractors with the numerous angles to be treated but, says Andreas Nordström, “It is the trickiest element but we are confident that the Aquajet’s unique control system will help us to remain on schedule.”
In total, the contract calls for the removal of more than 162 m3 of concrete from the dam and 439 m3 for all three spillways.
Freezing temperatures
The probability of night-time temperatures plummeting to below -20ºC is the principal concern for the sub-contractor throughout the winter months’ operations.
“Currently, in mid-October we are experiencing daytime temperatures of -9ºC,” confirmed Andreas.
“With the downstream river already frozen for the winter, the project could become a giant ice cube. Today is only -7ºC but by the night it is getting much colder.”
To prevent the hoses freezing overnight, E-Schakt has resorted to continually pass water through the high pressure hoses throughout the night and disconnecting the power pack, pass the water into the downstream river.
A heated circuit is also maintained in the water pumps 24/7 operation and antifreeze is also applied to the hosesA heated circuit is also maintained in the water pumps 24/7 operation and antifreeze is also applied to the hoses.
“It’s about preparing for the night-time temperature drop, otherwise we will have a real problem next morning,” he added.
First thing each morning, high pressure air is flushed through the hoses to clear the antifreeze before reconnecting then to the power pack.
Similarly during daytime breaks for meals and meetings, equipment is kept in ‘idle’ rather than shutting down.
Throughout each 12 week contract, E-Schakt has a team of three operators working a 12 hour shift, 7 days a week on a 7 day changeover cycle.
Järpströmmen hydropower station
The power station was built in 1944 and features three 118 MW tubines providing 415 GWh/year of electricity for the national grid.
Featuring a fall height of 66 m to the underground plant, the turbines are fed by a waterflow of 220 m3/sec from the 156 km2 lake Kallsjön, Sweden’s sixth largest lake with a depth of 134 km.